Friday, November 20, 2009

Painting...


The painters have started - both the interior and exterior of the house are now primed. The paint should be completed towards the middle of next week.

Installation of the floor tile will start on Monday, and the solar water heating panels will probably be installed next week as well (we're waiting for an appointment).

We poured the concrete countertop for the master bath last weekend - I will be taking it out of the mold this weekend to see how it turned out. I'll also start welding together the vanities for the powder room and the master bathroom this weekend. We're using square-stock steel to build those.

We also met with the welder that will be putting together the railings for the front and back balconies. He is scheduled to complete that work next week.

We seem to still be on schedule to finish the project by 12/15, which would be nice, since it would give us a week or two to get moved back in before Christmas.

Click here to see primer-iffic pictures.